RSS

Archive for the ‘Articles’ Category

St. Vincent’s (A Lesson Learned the Hard Way)

Wednesday, June 30th, 2010

The precipitous collapse of St. Vincent’s came as a shock to many, if not most Village residents. It shouldn’t have. Despite the dense obfuscation by the hospital’s administration, there were adequate signs for all to see.  While there is little to be gained from finger-pointing, understanding what went wrong offers valuable lessons for addressing future issues facing the Village, other historic districts and communities throughout the City.

Land is a finite resource and land within historic districts is a particularly scarce finite resource. Institutions, such as hospitals and schools, which deliver services on a face-to-face basis need space from which to deliver these services. In general, serving more people requires more space and one of the claims made by St. Vincent’s throughout the hearing process was that the new building was needed to meet expanding demand for its services. The capacity to add space and to provide for temporary accommodation during renovation, especially in an historic district, is one of the most valuable assets available to an institution.  One need only look at the ongoing problems faced by both Columbia and NYU in finding opportunities to meet their expanding space needs, or, for that matter, the Department of Education’s difficulty in finding locations for new elementary and intermediate schools.  With this in mind, a red flag should fly when an institution that claims to be growing seeks to sell three-quarters of its land, ostensibly to insure long-term survival.  In the case of St. Vincent’s, even had the new building been economically feasible which certainly appears not to have been the case, the sale of the East Campus would have left the hospital so tightly crammed into an architectural straitjacket with so little swing space that accommodating changing technologies would have been very difficult at best, and likely impossible.  Looking only at the physical constraints, the Rudin/St. Vincent’s plan was not a viable plan for healthcare in the Village or, for that matter, for the west side of Manhattan. This, in itself, should have raised skepticism if not outright disbelief.

The financial conditions, even as they were generally known from the time of St. Vincent’s emergence from bankruptcy in 2007 until the impending collapse became publicly known in late 2009, should have given added warning. In 2007, St. Vincent’s was carrying a $700 million debt.  The sale of the East Campus would have covered less than half of that amount. With more than $400 million in debt carried forward, obtaining financing for a new facility that was estimated to cost nearly $1 billion seems unlikely to say the least.  Even if this had happened, it seems doubtful that the hospital could have remained viable while supporting a debt burden of nearly $1½ billion.

And however dark the pre-collapse outlook may have appeared to those on the outside, it was far less dire than the actual conditions, conditions that must have been known to the hospital’s leadership.  Based on reporting in The New York Times and Crain’s New York Business, we now know that the debt has grown to something over $1 billion, an increase of more than $300 million in three years or average losses of more than $8 million per month. St. Vincent’s argued or at least strongly implied that the new building was the key to its financial viability; however, if the project had gone forward and was completed in four years, a highly ambitious schedule, the intervening 48 months during which the hospital would have had to continue in its present facilities would have added yet another $450 million in debt. In other words, given the current debt, the added operating debt incurred during construction and the cost of construction itself, and allowing for the income from the sale of the East Campus, based on what we now know, St. Vincent’s would have moved into its new facility owing more than $2 billion. Even with subsidized construction financing, this hardly seems like a realistic plan.

In early 2010, the public is just beginning to understand the full extent of St. Vincent’s problems. Given the revelations that are occurring almost daily, the emergence of additional concerns would not be unexpected. On the other hand, again based on newspaper reporting including coverage of the recent bankruptcy filing, the people responsible for management and long-term planning for the hospital must have known for several years that this day was coming. Despite this, the situation had reached a point in January that it was only the last minute infusion of millions of dollars from the State and the creditors that prevented the immediate closure of the hospital. The threat was that without a massive bailout, St. Vincent’s doors would be locked within days or weeks at the most. As it turns out, the results are only marginally better with the shutdown spanning a few months rather than days.

What does all of this say to our community, to historic districts in general and to our society as a whole?  First and foremost, we must insist that the critical decisions that affect us all be based on hard facts and, when analyzing these facts, that we avoid diversions. Looking back on the presentations at the Landmarks Preservation Commission as well as at Community Board hearings and other public events, the discussions of adding or removing a floor or two, changing the shape of the curved wall of the tower, the color of the wall cladding or revising the window layout seems ludicrous. A 2015 St. Vincent’s Medical Center $2 billion in debt is not and never was a realistic option. Further, compressing most of the 2008 hospital program onto a piece of land about one fourth of the current site seems so highly questionable that the question has to be raised as to whether it was ever a serious proposal.  Finally, although the $300 million sale price of the East Campus is a substantial sum, it represents only 15-20 percent of the money that St. Vincent’s would have needed to construct its new facility and to clear up its debts. This seems a staggeringly small amount for the abandonment of its prime physical resource.

To recap, from the outset of the discussions regarding St. Vincent’s attempts to sell the East Campus and relocate onto the O’Toole site, we have known, or should have known, that the undertaking would still have left the hospital very deeply in debt and with a physical plant that would have been profoundly problematic if not completely unworkable. That the project got as far as it did is testament to the fact that the developers were able to keep discussions focused on details rather than on the big picture.  We must not allow this to happen again. For decades, the stated mission of St. Vincent’s – to provide health services to the City as a whole – has informed public planning and zoning decisions affecting the site. This has included a number of very significant concessions that would not have been given to other applicants. As such, any plans for the future use of the East Campus must consider how this critical resource may continue to support community or public purposes, for healthcare or other vital services. Until this is done, I believe that it is imperative that any decision regarding the future of East Campus be reserved. As I said at the outset, land, or in this case real estate, is a finite resource. It is also essentially a non-renewable resource.  Once it’s gone, it cannot be reclaimed within a meaningful timeframe. We must not let this tremendous resource be lost to trivial usage.

Carl Stein, FAIA Principal
Elemental Architecture LLC

(Reprinted from the Greenwich Village Block Associations News  Spring 2010)
To view the entire edition click here.

New York Times Op-Ed: Don’t LEED Us Astray

Monday, May 24th, 2010

In the May 19th issue of the #NYTimes, Alec Appelbaum writes a well positioned Op-Ed piece on the question of green, LEED-rated buildings potentially loosing their luster once in full operation.  Mr. Appelbaum essentially promotes the idea of a creating an incentive program for buildings to go beyond LEED certification, a benchmark that many new construction projects can achieve, and that those buildings should receive credits/subsidies to maintain and promote further energy and resource conservation – a position we fully support.

While we’re fully in support of LEED and the sea change it has created,  Mr. Appelbaum’s view and critique of where LEED certification leaves off is one we also maintain.

Read the full piece here.

Carl Stein – Renewable Energy World North America: “Renewable but Finite”

Thursday, December 3rd, 2009

Carl Stein’s article in Renewable Energy World North America ‘Defining Renewable’ segment is available in print and for download now.

Renewable Energy

As Carl concludes:

“With remarkable shortsightedness, we have come to believe that the petroleum-era paradigm which was made possible by the availability of plentiful, cheap energy represents the natural order. In fact, it is not sustainable and is tending toward catastrophic results. The shift to renewable energies as our primary resources will reconnect us to the cultural/ethical continuum of humankind; a new paradigm.”

Read the article here. or download PDF .

PlaNYC proposal calls for energy audits of buildings 50,000 sf or more

Thursday, October 15th, 2009

According to a NYT article, as part of Mayor Bloomberg’s PlanNYC, a proposal seeks to employ mandatory energy audits of existing structures of 50,000 square feet or more and requires owners to make certain improvements to make the buildings more energy efficient. James F. Gennaro, chairman of the council’s environmental protection committee and a sponsor of the measures, says “Eighty-five percent of the buildings that we have in 2009 are going to be here in 2030.”

Administration Urges ‘Hard Changes’ in Green Mindset

Friday, September 25th, 2009

Director of long-term planning and sustainability for the Bloomberg Administration Rohit Aggarwala tells an audience at The Urban Green Council (the newly renamed NY Chapter of the USGBC) that the building community now needs to address questions that go beyond a property’s design and construction. Aggarwala cites an important example to consider how a property can be truly green if there are no leasing requirements in place to ensure it’s operated in an eco-friendly manner. At present, there is no standard in place to determine the owner’s or tenant’s responsibilities for sustainable operation. While the general perception of sustainable buildings is  new construction, “if we’re going to make our big cities greener we have to focus on our existing buildings,” Aggarwala said.

Elemental has actively engaged its commercial clients, particularly building Owners and managers, to offer leasing structures which allow ‘green’ tenants to benefit directly from the economic savings of resource conservation. Suggested measures include individually metering electricity, heating, cooling and water use – and allowing the data of their use to be analyzed/displayed in real-time – as well as  energy and resource efficient upgrades for windows and plumbing fixtures which further reduce energy use for heating, cooling, domestic hot water and circulation. Individual tenant metering means that each tenant can reap the dollar savings resulting from those energy upgrades. In short, energy conservation by Owners can translate into economic benefits for every tenant.

Read more on Aggarwala’s address here: