Construction Update: Shepard Hall Original Entry Stairs Revealed
As demolition and excavation progress continues for the newly designed building entry, a startling discovery: the original entry stairs built in 1907, long believed to have been demolished, are found buried under earthwork fill below the recently removed concrete ramp. Along with the stairs a significant portion of original schist stone wall is also uncovered. Elemental and the construction team are now evaluating if portions of the original elements can be incorporated into the new entry design.

Tags: elemental, elemental architecture, historic reconstruction, landmark preservation, Shepard Hall
Thursday, September 3rd, 2009 at 1:51 pm • Architecture, Construction Update • RSS 2.0 feed • leave a response or trackback
[...] construction continues, efforts to utilize the original schist stone entry ramp wall that was recently unearthed continue to make progress. Concrete underpinning (for an explanation of underpinning, click here) [...]